NHS provides answer to impossible deadlines
A change to building specs that’s just not possible
in the project time frame? This client knew where to go
for the answer and Wernick provided it.
For George Rankin and his team at Studio Four Architects
in Romsey it was just another interesting day nursery
project, similar in many ways to another building they
had recently completed for the Southampton University
Hospitals NHS Trust. But this one was due to change
radically before the ink had dried on the agreed sketch
drawings and specification when the client stipulated
that an extra 879 square metre floor of offices for the
Southampton City Primary Care Trust needed to be added
above the 1063 square metre ground floor day nursery,
crèche and training centre. This was not the first time
in his 35 year career that George had been confronted
with a challenge like this, but he knew that this
addition to the design for the Trust Taplins Childcare
Department at the Western Community Hospital was just
not possible using traditional construction techniques
within the time frame imposed by funding constraints.
Fourteen months had been allowed for the project from a
‘cold start’ through briefing, full design, approvals,
tender and completion of the site construction, and the
days were disappearing fast! It was the client who came
up with the solution – modular build, but George freely
admits that this was one of those rare occasions when he
had to swallow his professional pride, “Because”, as he
explained later, “modular would not have been my first
choice of build technique”. As it turned out George and
the client were delighted with the end result that came
complete with a traditional brick skin and pitched roof.
The funding arrived on time and the project was
completed within budget, on time.
Modular specialists Wernick Buildings won the factory
build project in a competitive open tender against stiff
competition from three other companies because they were
able to offer a cost-effective, traditional-looking
building, constructed under tight quality control
conditions at their manufacturing plant in South Wales,
and all completed within the tight programme
requirements.
With funding from seven different bodies the new £2.3m
facility has space for 100 children. Half the places are
allocated to children whose parents work in the local
NHS, with the remaining 50 allocated to children from
families living in the local community. In addition to
the nursery, there is a training suite on the ground
floor, complete with IT room and separate crèche, which
is available to staff and child-care providers such as
the Early Years Partnership, who require a training
resource in the area.
In addition to the usual childcare amenities, the Centre
has indoor and outdoor play areas, quiet rooms and
sleeping areas. The nursery is managed by Taplins, the
internal childcare department of Southampton University
Hospital Trust.
Nursery Manager, Sam Hollins commented, “It’s a great
new child care provision for the local area, with a safe
and inspiring environment in which children can be
professionally cared for. We particularly like the
all-weather garden which is covered in ‘no mow’ grass
that looks and feels really convincing”.
So after a thumbs-up from the design professionals and a
thumbs-up from the childcare professional end users,
does George Rankin think that architects know enough
about modern modular building techniques? “Definitely
not”, he stated, “We are not fully aware of its
strengths and weaknesses. For some sites it’s ideal and
for other sites, as we found out, it’s the only answer!
The majority of people would never guess that this
project, with its brick skin and traditional roof, is
not a traditional build. Architects need to sit down and
develop modular principles with companies such as
Wernick as we are not fully aware of the system’s full
potential, and when we get a panic job like this one
there is just is not the time to investigate the
technique fully”.
Email:
sales@wernick.co.uk
Bosch Security Systems Video Management Systems Modular Camera System news
240306
Briggs & Forrester Contracting Building Services Specialists news 280306
Challenger Security Systems CCTV Access Control news 280306
CIOB Health and Safety Building Control Standards news 300306
Crimp-Pak
Cable Ties Crimp Tools news 280306
Elesta UK Boiler Control Building Management news 230306
Emitex
Cable Management UPS Static news 240306
Evac+Chair International Ltd Lifts Escalators Disabled Facilities Hoists news
290306
Frenger Systems Chilled Beams Radiant Heating Panels news 300306
Hazardous Area Equipment Fluorescent Light Fittings Bulkheads news 280306
Hi-Tec Spray Spray Painting Equipment Surface Coating news 280306
Honeywell Control Systems Ltd Radiator Thermostats Surface Mounted Thermostats
news 200306
Honeywell Control Systems Ltd Valves Pipework Systems Motorised Valves news
270306
Hydroscape
Water Feature Design news 280306
MDF Specialised Coaters Ltd Powder Coating MDF news 230308
Playworld Systems Europe Outdoor Play Equipment news 200306
Renderplas Internal Wall Finishes Plaster Lining Moulding news 310306
Siemens Building Technologies Variable Speed Drives Valves Actuators news 230306
Toolstation Tool Station Hand Tools Power Tools news 240306
Totty Construction Building Services Consultants Building Services Contractors
news 310306
Totty Construction Building Services Contractors Building Services Consultants
news 280306
Tyco Thermal Controls Floor Heating Cooling Temperature Measurement news 310306
Verint Systems Digital Video Security Surveillance news 300306
Vision Fire & Security Perimeter Protection Security CCTV Cameras news 300306
Ward Insulated Panels Ltd Single Ply Roofing Systems news 230306
Wernick Buildings Ltd Modular Building Construction Installer news 230306
Wernick Buildings Ltd Modular Building Construction Installer news 230306
Wernick Buildings Ltd Modular Building Construction Installer news 230308
Arundel Jones Associates LLP Registered in England and Wales No.
OC330189 Hill Farm, Linton Hill, Maidstone, Kent ME 17 4AL Tel : 01622 745333
email copyright all rights reserved
News Categories : Modular Building Construction
Installer
|