Bachy Soletanche develops piling solution at Liverpool Heritage Site
Leading geotechnical specialist, Bachy
Soletanche Limited has provided an innovative piling solution at
Liverpool’s Half Tide Dock, using a bespoke piling method in
order to preserve a heritage dock wall adjacent to the site. The
fast-track project, completed late last year will support the
construction of a nine-storey luxury apartment block in the
popular waterfront location on Liverpool’s dockside.
The development will form part of the final stages of the
regeneration programme for Liverpool’s 2008 European Capital of
Culture programme. The piling contract, worth £180,000 for Bachy
Soletanche, was completed in a strict four week schedule, with
the new residential building due to be finished before 2008. The
prestigious waterfront development will comprise one hundred and
twenty-one residential apartments, accompanied by underground
parking.
Steve Mallinson, Contracts Manager at Bachy Soletanche Limited
commented:
“The plans for the latest addition to the dockside residential
area required only straightforward piling at first glance – but
we were then made aware of the heritage status of the dock wall.
This meant we had strict guidelines to adhere to, and the wall
was not to be affected in any way from the nearby drilling and
pile construction. As such, we installed permanent liners of
750mm diameter for the piles that fell within close proximity of
the wall - ensuring the development had the required level of
support whilst preserving the integrity of the heritage dock
wall”
The new design meant that seventeen out of the total eighty-four
piles were constructed using permanent steel liners surrounding
the main body of the pile, each 750mm diameter. The liner
effectively de-bonded the pile over the top 10metres of the pile
and ensured no load was transferred from the pile to the
surrounding ground and hence the dock wall.
Steve Mallinson continued:
“By constructing the permanent steel liner around the piles we
could ensure that no load would transfer between the pile and
dock wall. As such, no impact was made to the surrounding area
at any point during the process and the strict guidelines for
protecting the wall were adhered to fully.”
The first row of piles, which ran parallel to the dock wall
consisted of seventeen LDA piles, each with a depth of 14
metres. It was for this initial row that the steel liner process
was used. The piles were bored with a 10.0m rock socket, however
7.0m of this was de-bonded with the liner. The remaining
sixty-seven piles were constructed using the faster CFA process,
with piles bored to a depth range of 8-9metres.
Steve Mallinson continued:
“The combination of the CFA and LDA piles alongside the bespoke
design allowed the project to run smoothly and within the
four-week deadline.”
“This project is a great example of how bespoke designs can
bring huge benefits to smaller contracts, as well as the larger
projects with which this type of intricate process would be more
commonly associated.” He added.
Bachy Soletanche has already completed a range of works
throughout Liverpool as part of the Capital of Culture 2008
programme, including high-profile work at Kings Water Front in
February 2007 on the other side of the River Mersey.
Steve Mallinson explained:
“Bachy Soletanche provided piling for the arena and the
conference centre at the Kings Water Front project, as well as
the multi-storey car park to be situated on the site, in a
two-phase project worth a combined £3.2million. Much larger than
the work at Half-Tide Dock, the piling work included 800 CFA
piles and 420 LDA piles constructed within a four month
schedule.”
“The Liverpool 2008 European Capital of Culture has been an
excellent opportunity to regenerate the city and we at Bachy
Soletanche are delighted to have been such an active part of
it.” He added.
Email:
Fiona@manifestcomms.co.uk