DANFOSS - Energy efficient Cooling At Aarhus University Hospital
A new centralised cooling plant will annually save 800,000 kWh energy and secure
optimal operation at Denmark’s second biggest hospital.
Stability and efficiency are key words at the new centralised cooling plant at
Aarhus University Hospital, Skejby. This, the main hospital of Denmark’s second
largest city Aarhus, has replaced a huge amount of old decentralised cooling
units with one, new centralised plant with a cooling capacity of 2.5 MW. It
improves the level of stability of the necessary cooling of surgery rooms,
scanners, server rooms and IT-equipment.
At the same time it facilitates the possibility of the operations department to
control and run the complete cooling plant more effectively - with much lower
energy consumption than before. It is estimated that the hospital will save
around 3.5 mio kWh of energy annually, due to the installation of a highly
energy efficient heating and cooling system. The new system combines the cooling
system with the heating system, an obvious solution, which is not used very much
worldwide.
High efficiency heat pumps and chillers
The new cooling plant consists of two large air/liquid heat pumps, 9 air-cooled
chillers and a number of compressors. The units are called SAB LightTM from
Johnson Controls. Danfoss VLT® drives control the speed of the units. The new
technology used combined with the frequency converters contribute to the total
energy savings.
During the months of June, July and August the heat pumps are able to deliver
all the heat required at the hospital. Therefore no extra heat has to be
delivered from the public district heating network. Surplus heat from the
cooling production during the summer is reused for heating purposes. During the
winter the heat pumps deliver a smaller portion of the heat consumption, while
the main heat supply is taken care of by the district-heating supplier,
AffaldVarme Aarhus.
The two 180 kW heat pumps (actually two times two separate heat pump circuits,
which are built together into one unit) are designed for temperatures of 35/80
C. They achieve important energy savings, due to the fact that they re-use the
heat instead of exhausting it into the air. ”The heat pumps´ COP (coefficient of
performance) is 3.6 or more, depending on outside temperature and cooling
demand. This means that their heating power is 3.6 times the electricity
consumed. On the old system, the COP was only between 2 and 3, so the heat pumps
are an energy saving solution”, says Svend Madsen, Sales/ Project Engineer from
Johnson Controls, who have installed the cooling plant and hold the service
agreement. Svend goes on to say “Compared to 10 decentralised cooling plants
running separately, which was the situation before, there are huge energy
savings in co-ordination and control of the different units (heat pumps,
chillers etc.).”
The chillers´ COP is 5 or more depending on cooling demand and outside
temperature. The 90 kW VLT® drives from Danfoss, combined with the control
system, regulate that only the required cooling is actually being produced A
small 5.5 kW VLT® drive runs a pump on the cooling system and is regulated
according to the speed of the big VLT® drive depending on cooling demand.
Easier control and service
A new PLC monitoring system measures and analyses the efficiency of each machine
in order to secure the right combination of chillers and heat pumps, so that the
most energy efficient production is chosen at any time. For instance, the
supervision can change the production from three chillers at maximum load to
four chillers running at 80 % load, based on a snapshot on what achieves the
biggest energy savings. This way the CO2 emissions are reduced as much as
possible.
Svend Madsen explains that the cooling plant also uses free cooling in the
wintertime in order to utilise the cold days of the year, so no cooling is
produced during this period. “It’s also very important in the attempt to save
energy that surplus heat from the chillers is re used for heating purpose
instead of being sent into the air,” he says.
The highly efficient centralised cooling plant is easier to monitor, control and
service than the many old cooling units. There will be less maintenance work to
do for the operating staff. “The entire system is computerised and PLC
controlled, so the physical monitoring will be brought to a minimum. In the
design phase and during the installation process we have cooperated closely with
the operations department. They are the ones who will work with the plant on
daily basis, so their input is important for the project”, project manager Lars
Torp Larsen from consulting engineer Alectia says.
If, for instance, one cooling machine has a lower performance than the others,
the staff will be warned by an alarm an immediate action will be taken to
optimise it. A CTS system monitors a number of parameters, which takes care of
the efficiency of the IT monitoring system. Poul Hvid Nielsen, Chief of
Technical Department at Aarhus University Hospital, Skejby, is satisfied: “In
this way the hospital has got double security for optimal operation. Being a
hospital, security of supply is fundamental to us”.
Hospital enlargement on the way
Poul explains that three new buildings have been built and added to the hospital
recently, and the new centralised cooling plant is prepared for a further
growing demand for cooling. ”The cooling system is designed so that, for
instance, a cooling machine or a heat pump can cut out on a warm summer day
without creating any kind of problems to the cooling supply”, he says.
The hospital is one of Denmark’s most important hospitals and will be enlarged
to more than double the size over the coming years. “The project group has
worked on achieving synergy in the process of renovating the existing hospital
and at the same time enlarging it to almost twice the size. I think we are
succeeding in this”, Poul says. However, the newly established cooling plant
will not be able to supply the many new hospital buildings to be built in the
coming years. Instead, a second cooling plant will be built and the two plants
will supplement each other to fulfill future cooling needs.
Environmentally friendly solution
”Since several of the old cooling units were worn out and needed to be replaced,
something had to be done now. There was no possibility of waiting until the new
parts of the hospital are built. The new cooling plant is not only more
efficient but also more environmentally friendly than the old system. Many old
units used the greenhouse gas Freon 22 as refrigerant - this is forbidden in all
new cooling systems in Denmark, and at Skejby Hospital it has been replaced by
natural refrigiants. The choice fell on chillers using R290 (propane, GWP*=3.3)
and heat pumps using R600a (iso buthane, GWP=4). Other options like CO2 had also
been evaluated but were found to be less efficient in the applications and the
temperatures required. This way about 750 tons of CO2 emissions are saved
annually”, Lars Torp Larsen says. Moreover, the new cooling system saves around
800,000 kWh of energy per year and surplus heat from the cooling plant is
reused.
*GWP = Global Warming Potential
All the environmentally friendly results are additional benefits of the
installation of a much better cooling system, where state-of-the-art energy
technology is being used to the benefit of the hospital patients and its staff.
Facts about the VLT® drives
• Installed on each chiller are: a VLT® HVAC Drive FC 102 90 kW, IP55 enclosure,
EMC filter , a safe stop and graphic display with an integrated service switch,
in order to run the compressor (11 units).
• Installed on each heat pump are: a VLT® HVAC Drive FC 102 90 kW, IP55
enclosure, EMC filter, a safe stop and a graphic display with an integrated
service switch, in order to run the compressor (2 units).
• Each chiller also features: a 5,5 kW VLT® HVAC Drive FC 102 IP55 with an
integrated service switch to run the pumps (14 units).
• Installed on the central pump are: a VLT® HVAC Drive FC 102 37 kW, IP55, EMC
filter, safe stop and graphic display with an integrated service switch and a
corresponding 5,5 kW drive (2 units).
Facts about the cooling plant
• Minimum load on cooling demand is 350 - 450 kW annually.
• The heat from previously used air is separated and sent into the heat pumps
and reused. This saves electricity and minimises CO2 emissions.
• All in all the cooling and heating systems of the new cooling plant will
result in energy savings of 3.5 mio kWh annually and a reduction in CO2
emissions of 750 tons annually.
AkzoNobel Dulux paint Trade paint Decorative paint Gloss paint News
161211
Cembrit Roof tiles Slate tiles Slate roofing Roof cladding News
151211
Danfoss Ground source heat pumps Heat pumps Inverter drives News
151211
Dimplex Air source heat pumps Heat pumps Renewable energy News
161211
Dorma Access control Door closers Door hardware Door operators News
161211
Dulux paint Dulux trade Trade paint Exterior paint News 151211
Dulux paint Dulux trade Trade paint Gloss paint News 131211
Eaton Electric Switch gear Fuse boards Lighting controls Speed
drives News 161211
Gent Fire alarms Fire detection Alarm systems Emergency lighting
News 131211
Kingfisher Ventilation louvres External lighting Flood lighting
Industrial lighting News 121211
Leaderflush Shapland Door sets Timber doors Door hardware
Architectural hardware News 161211
Marshall-Tufflex Cable management Energy management Cable trays Data
services News 121211
Prysmian Fire cables Armoured cables Power cables Energy cables News
151211
Space Air conditioning systems Air cooled chillers Air conditioning
News 151211
Steadmans Wall panels Roofing materials Roof panels Insulated panels
News 161211
Tyco Thermal Controls Trace heating Frost protection Pipework
insulation Underfloor heating News 151211
UPS Ltd UPS systems Static UPS Modular UPS UPS products News 151211
News Categories:
Heat pumps Speed drives Inverter drives Danfoss drives
Arundel Jones Associates Ltd Hill Farm
Business Park, Linton Hill, Maidstone, Kent ME17 4AL
Tel : 01622 745333
news@buildingdesign.co.uk
See also:
| BuildingDesign Directory
|
BuildingDesign Tenders |
|BuildingDesign News Archives
| 2006 |
2007 |
2008 |
2009
|
BuildingDesign Recruitment |
AJA Part Time Jobs Board
|
© 2010 copyright all rights reserved
Registered in England and Wales No. 07334149
|