Fast track installation of ceramic tiling
Introduction
Where building programmes are short and/or cost
penalties high, the designer has to take advantage of
every material and technique that allows ceramic tiling
to be installed and serviceable within the contract
time. Fast track installation of tiling can reduce the
contract time by hours, days or even weeks as long as it
is planned within the scope of works; and the increase
in material cost is easily offset by the savings in time
that can be achieved.
Objective
There are two basic areas relating to ceramic tiling
that can be considered appropriate for “fast track”
working. The first relates to a completely new
installation, i.e. the construction of the background
and the installation of the ceramic tiles within a
limited time period, thus achieving early completion.
The second relates to the installation of the ceramic
tiles to an existing area so that the location can be
put back into use without undue delay. Examples would
include station platforms, fire stations, retail outlets
that are trading, car showrooms, etc.
The installation of rigid finishes such as ceramic tiles
using normal techniques places constraints on the time
taken to complete the installation, not only with new
build projects but also with refurbishment projects.
This is due to the fact that rigid finishes require that
the background is stable and in particular has finished
undergoing shrinkage. Shrinkage is a phenomenon that is
characteristic of cement-based materials such as
concrete, screeds and render but also applies to gypsum
plasters, blockwork walls, etc., and all backgrounds
that frequently require tiling. Shrinkage of such
materials can take weeks or months to complete; time
scales that are not commensurate with “fast track”
working. This paper is intended to give an overview of
techniques and materials that can be used to overcome
the fundamental problem of reconciling long term
shrinkage with “fast track” working.
Fast track work in ceramic tiling can be defined as the
installation of ceramic tiles so that the installed
ceramic tiling can be in use in a shorter period of time
than would be achieved using normal materials and
conventional techniques. Many fast track installations
are in critical situations where it is essential to get
it right first time, as it may not be practicable to
easily carry out repairs if problems subsequently occur.
There are advantages in the completion of a construction
project within a set time and in the commercial sector
the earlier the building is in use and earning money the
better it is for the client’s finances. Obviously the
shorter the construction times the greater the
advantages. This applies just as much to the
refurbishment projects and early completion can be even
more advantageous if the circumstances require the
complete closure of an existing facility. There are
limits however; these can be practical difficulties of
having too many people working in one location at the
same time; the temperature on site being too low and
other conditions that cannot be controlled. Similarly
using a rapid hardening adhesive to save a few hours may
not achieve the objective if 3 weeks have had to elapse
for the screed to finish drying and shrinking.
Normal constraints
Before considering the possibilities of shortening the
tile installation times it is worthwhile to outline the
conventional constraints that apply to normal ceramic
tiling. If new backgrounds installed to receive the
ceramic tiles are subject to drying shrinkage then most
of this shrinkage should take place before the ceramic
tiling is adhered to the background. Note that where new
backgrounds are constructed of several separate
applications of materials the drying times of each
application are cumulative and not concurrent.
A typical example would be a wall constructed of
concrete blockwork that has to dry for at least 6 weeks
before the first coat of cement and sand render is
applied. If more than one coat of render is to be
applied the first coat of render should be cured for a
few days (prevent rapid drying of the surface) before
being allowed to dry, shrink and harden before the next
coat of render is applied. The final coat of render
should be wood float finished and has to be cured for a
few days and then allowed to dry for at least 2 weeks
before the ceramic tiles are installed.
These cumulative drying times have to be considerably
extended in adverse site conditions, as the drying and
consequent shrinkage of the backgrounds will be very
slow if the temperature of the background is low. Some
European countries take a more realistic approach and
the minimum drying times of backgrounds to receive
adhered rigid finishes are considerably longer than
those recommended in the British Standard Codes of
Practice. For instance in Germany the drying time of
concrete is accepted as taking 6 months whilst in the UK
the British Standard gives a minimum of 6 weeks under
good drying conditions. The key word here is “minimum”;
it may take considerably longer under typical UK
conditions!
Even where refurbishment work is carried out, either
some new backgrounds have to be constructed or old
backgrounds reconstructed and there will be delays
caused by the required drying times of in situ applied
backgrounds.
Potential problems
Ceramic tiles are characteristically hard and brittle,
with a high Young’s modulus of elasticity. A slight
lateral compression of the ceramic tiles can develop
extremely high levels of stress particularly where the
ceramic tiles are fixed with adhesives since adhesion to
strong backgrounds is usually good. If the stresses
exceed the restraint between the tile and the background
the ceramic tiles will debond with the ceramic tiles
bulging out from the background. The amount of bulging
out or debonding may be only slight but tends to occur
away from movement joints as the stresses tend to be
more concentrated in the centre of an area of ceramic
tiling.
If the correct design criteria are not addressed, or if
the materials used to install the ceramic tiling do not
have the necessary properties, then problems can occur
with the installed ceramic tiling. Background shrinkage
after the ceramic tiles have been installed is the most
common cause of problems with ceramic tiling where not
enough time has been allowed for the background to dry
sufficiently before the ceramic tiles were installed.
The problems usually do not occur until several months
or even a few years have elapsed after the installation
had been completed; though under certain conditions some
problems have shown up even before the contract had been
completed. The heating up of the building after
completion can cause renewed background shrinkage, as
drying down to a moisture content in equilibrium with
the warmer and drier conditions will occur.
The rapid increase in the use of underfloor heating,
either embedded in the underlying screed or with some
refurbishment systems within the tile adhesive bed
itself, has added to the potential problems both in
terms of the conditioning required to stabilise the
system and in respect of the consequent thermal cycling
from the use of the heating system.
When the backgrounds continue to shrink (and expand with
underfloor heating) after the ceramic tiles have been
fixed the installed ceramic tiling is laterally
compressed and such stresses are not relieved by the
insertion of so-called stress relieving joints in the
tile bed. With weakly adhered ceramic tiles, such as
those fixed with cement and sand mortar, the stresses
can result in the tile bed debonding at the stress
relieving joints.
Prefabricated backgrounds
The use of certain prefabricated backgrounds, such as
wood-based sheets and boards, can present problems as
such boards will not be dimensionally stable with the
moisture content of such boards fluctuating as the
atmospheric humidity rises and falls. Ceramic tiling on
one side of such boards essentially produces an
unbalanced construction and if the board absorbs
atmospheric humidity, or more frequently dries after the
installation of the ceramic tiles, warping will occur
with the likelihood of cracks developing at the board
joints.
The recommendations in the British Standard Codes of
Practice to have dry wood-based boards, with the backs
and edges sealed to prevent the ingress of atmospheric
humidity and rigidly fixed and braced, is difficult to
achieve in practice. The conditioning of the wood-based
boards, by drying them down to the moisture content that
matches the long-term moisture content of the boards
once the building is in use, can be difficult to
achieve, particularly if the building is subsequently
heated. Note that certain building boards that are not
wood-based may also show dimensional changes with
moisture content so they should also be conditioned to
an appropriate moisture content before the ceramic tiles
are fixed.
Solutions by design and materials
The problems of the required drying times can be
by-passed by utilising certain design features and
materials that overcome the inherent problems of using
normal techniques to install the ceramic tiles. The
selection of the background at the design stage can make
a big difference by allowing the installation of the
ceramic tiling to proceed almost as soon as the new
backgrounds have been installed.
These design decisions can include the use of certain
prefabricated backgrounds, such as stable boards on
walls and rapid drying materials that dry and complete
shrinking within hours rather than days. Materials such
as ARDEX AM 100 one coat tiling render or a bonded ARDEX
EB 2 rapid hardening floor screed will allow tiles to be
fixed in hours rather than after weeks, even unbonded
cement/sand screeds may be tiled after 24 hours if ARDEX
A 35 rapid drying cement for floor screeds or ARDEX A 35
MIX rapid pre-blended rapid drying screed mortar are
used. The decision to use rapid setting, rapid hardening
and rapid drying adhesives and grouts will enable the
ceramic tiles to be fixed and grouted within a very
short time period.
The application, where appropriate, of paper-faced
plasterboard is an effective solution for many internal
walls in dry locations that are exposed to normal use as
a background for ceramic tiling. In areas where the
ceramic tiling is in wet and humid areas, such as
showers, the use of proprietary boards specifically
designed for supporting ceramic tiling in such locations
will enable ceramic tiling to be fixed immediately after
the installation of the boards. Or alternatively the use
of waterproof coating systems such as ARDEX WPC flexible
rapid drying and setting waterproof coating allows tiles
to be fixed just 2 hours after the application of the
second waterproof coat.
Where the ceramic tiling is designed to be installed on
cement and sand screed over a new concrete base, then
the decision to use ARDEX A 35 cement, a special
proprietary rapid drying cement, to install the unbonded
screed over an effective slip/damp-proof membrane on the
concrete base will be effective.
The ARDEX A 35 cement will provide a screed that will
have dried and shrunk sufficiently rapidly to enable the
ceramic tiling to be installed just 24 hours later.
If an existing dry concrete base has to be tiled then it
is possible to utilise a bonded screed made with ARDEX
EB 2, a special proprietary rapid setting and hardening
cement, so that the ceramic tiling can be installed just
a few hours later. This system has the advantage that it
may be used in wet locations including swimming pool
surrounds and even in the pool itself. Adequate
preparation of the concrete base and effective bonding
of the screed should be specified to ensure good
adhesion between the bonded screed and the concrete
base.
Similarly, if existing walls have to be rendered it is
possible to apply ARDEX AM 100, a proprietary
cement-based render that will allow the fixing of
ceramic tiling after only 2 hours. This will only be
effective if the wall is of a suitable construction,
e.g. concrete blockwork, and clearly is adequately
mature and dimensionally stable.
Adhesive performance
The adhesives should be selected on the basis of the
most appropriate characteristics to suit the
circumstances on site. With floor tiling it may be
particularly important for the installed ceramic tiling
to be able to carry foot traffic a few hours after
fixing. In these circumstances the adhesive used will
need to have the properties of a short setting time,
rapid hardening and rapid strength development, for
instance ARDEX S 16 rapid drying tile and natural stone
adhesive is particularly suitable for this type of
application in dry locations and will allow grouting and
foot traffic within a few hours. If the time period
between fixing and carrying traffic is longer, e.g. 5
hours plus, then a normal setting but rapid hardening
adhesive with early strength development such as ARDEX-FLEX
S 38 flexible floor tile bedding mortar will be
suitable.
These criteria will have to include consideration of
other required characteristics, e.g. communal showers,
where the ceramic tiling will be exposed to wet
conditions and will require the adhesive to be
water-resistant (e.g. ARDEX-FLEX 6001 or ARDEX-FLEX S
38); where translucent materials, such as glass mosaics
are to be fixed, a white adhesive such as ARDEX S 16 W
rapid drying tile adhesive will be required.
A further consideration is that the adhesive must also
perform in the long term. Enhanced adhesive performance
will also help to minimise risks of failure at a later
date, as any stresses that were unforeseen at the time
of installation or were generated as a result of the
fast track working are more likely to be accommodated.
In addition sensitive backgrounds such as timber-based
boards or moisture sensitive natural stones will also
require an adhesive that is rapid drying as well as
rapid hardening. The latter two terms are often confused
but are very different.
A true rapid drying system such as those featuring ARDEX
Rapidry Formula technology, will dry by chemically
binding any free water into stable hydration reaction
products so that the material will dry even between two
non-absorbent surfaces and irrespective of application
thickness. The free water does not need to evaporate
away.
Grout performance
Typically, grouting must wait for 24 hours after fixing
the tiles; 48 hours in the winter; even longer for
swimming pools; these times can be reduced significantly
by using rapid hardening adhesives as discussed above.
The grouting of tile joints should commence as soon as
possible after the ceramic tiles are fixed and the
adhesive has hardened sufficiently so that the empty
joints do not collect dust and other extraneous
materials. The rapid setting and hardening adhesives
will allow the grouting to commence in as little as 2
hours after fixing but if the grouted ceramic tiling has
to be trafficked as soon as possible the grout mortar
will also have to harden rapidly.
The cement-based grout mortars can have rapid setting
and rapid hardening characteristics to enable the
ceramic floor tiling to be trafficked in as little as 1½
hours after the completion of grouting. Suitable
products include ARDEX-FLEX FL and ARDEX GK grouts that
are not only rapid hardening but are also suitable for
heavily trafficked locations such a shopping malls, etc.
The installation of finishes takes place towards the end
of any contract and is particularly important with
ceramic floor tiling as there should be provision for
temporary protection of the completed tiling if other
trades will be working in the same area.
Typical situations
Repairs to or the installation of ceramic tiling in
occupied premises will frequently be to mature
backgrounds so that the constraints of drying shrinkage
are not present or can be overcome by the techniques
outlined above. The adhesives and grouts used to install
the ceramic tiling should enable the ceramic tiling to
be fixed, grouted and put into use with the minimum
delay. Rapid hardening adhesives and grouts are
generally the preferred products for ceramic floor
tiling, whilst ceramic wall tiling is less critical but
the products selected have to perform adequately to
ensure completion is not delayed.
Some refurbishment and repairs in public areas require
all of the products used to install the ceramic tiling
to set and harden rapidly so that full use can be made
of the area within a short period of time. Examples
include public transport systems, fire stations,
airports, retail outlets and similar locations where
work has to be carried out during a very short time
period and the facility brought back into use within a
few hours. Here the adhesives and grouts used have to
set, harden and gain strength very rapidly so that the
public can have unimpeded use of the facility. In these
critical areas the installation has to be right first
time, as the consequences can be considerably
embarrassing if the installation fails to perform
adequately.
Note that repairs to existing tiling will frequently not
match the existing tiling due to wear and dirt
deposition. The grouting can also appear different in
colour as subtle differences in site conditions can
cause slight colour differences. These tend to become
less noticeable with time for floors as the surface is
trafficked.
The use of tile and grout cleaning systems can also
help, particularly for wall tiling.
Conclusion
The options have to be carefully considered and the
design has to take into account the environment where
the tiling has to be installed, the backgrounds to be
tiled as well as any requirement for early trafficking
or use. Fast track installation of rigid floorings is
possible, and can be very cost effective, when
appropriate materials and techniques are specified and
used.
Email:
info@ardex.co.uk
Pinelog Limited Log Cabins Lodges Summerhouses news 200706
Ardex UK Ltd Screeds Renders Ceramic Adhesives Grouts news 110706
ARDEX UK Screeds Renders Ceramic Adhesives Grouts news 200706
Briggs & Forrester Contracting Building Services Specialists news 200706
British Gypsum Ltd Plaster Plasterboard and Drylining Systems news 140706
British Gypsum Plaster Plasterboard and Drylining Systems news 190706
C & B Systems Pre-plumbed Panels Cubicles Sanitary Fittings news 120706
Ced
Limited cobblestone driveway paving news 200706
Chartered Institute of Building Conservation Maintenance and Refurbishment
Facilities Management news 170706
Cleansair Air purification units HVAC news 200706
Colt International Car Park Ventilation Smoke Control news 140706-1
Colt International Car Park Ventilation Smoke Control news 140706-2
Colt International Car Park Ventilation Smoke Control news 140706-3
Comar Architectural Aluminium Systems Curtain Walling Metal Cladding Facades
news 190706
Conder Products Sewage Treatment Septic Tanks Cess Pools news 120706
Dean & Bowes Retail New Build Leisure Building Fit Outs news 170706
Foremost Engineering Building Service Engineers news 180706
Formica Limited High Pressure Laminate formica furniture designs news 200706
Gent by Honeywell Emergency Lighting Fire Systems Detection Cabling news 170706
Greenstock Lamp Company Fluorescent Tubes Energy Saving Light Bulbs news 170706
Hunter Plastics Sanitary Concealed Systems news 130706
Jackson Construction Construction Services Specialists New Builds news 100706
Jackson Construction Construction Services Specialists news 200706
Kee Klamp Ltd disability guardrail handrail system news 130706
Marmax Products Ltd External Furniture Seating Litter Dog Waste Planters news
200706
MHS
Homes Construction New Homes Rental news 120706
Mita (UK) Ltd Cable Management Floor Boxes Underfloor Services news 210706
M R Site Services Ltd Architectural Steelwork Aluminium Roof Welding news 110706
Polyflor Ltd Flexible Sheet Tiles Carpets news 200706
Polyflor Ltd Sports Surfaces Safety Flooring news 120706
PRI Limited Measurement control and protection news 120706
PRI Limited Metering Systems Services Software news 120706-2
SAS International Architectural Steelwork Ceiling Systems Ceiling Panels news
170706
SAS International Ceiling Systems Ceiling Panels Tiles news 100706
Sun Shield Window Film Films for Glass solar control safety security news 210706
Thurston Building Systems Ltd Buildings Temporary Space Prefabricated Modular
news 120706-1
Thurston Building Systems Ltd Buildings Temporary Space Prefabricated Modular
news 120706-2
Totty Building Services Building Services Contractor news 120706
Twyford Bathrooms professional bathroom installations news 130607-1
Twyford Bathrooms professional bathroom installations news 130706-2
Videx Security Limited Door entry systems news 210706
Vision Fire & Security CCTV security surveillance news 210706
Wernick Buildings Ltd Modular building construction installer news 180706
Arundel Jones Associates LLP Registered in England and Wales No.
OC330189 Hill Farm, Linton Hill, Maidstone, Kent ME 17 4AL Tel : 01622 745333
email copyright all rights reserved
News Categories : Screeds Renders
Ceramic Adhesives Grouts Floor Screeds Resin Finish
|